Home Structure Armed Forces of the Russian Federation Air Force Falcons of Russia News Read more


25.05.2016 (23:17)

Tests are being completed power plant on the lead vessel of project 23120 "Elbrus"

Northern Shipyard completes testing of the main power plant of the lead ship logistics support project 23120 "Elbrus" for the Ministry of Defense of the Russian Federation - the equipment is working properly.

The power plant consists of four diesel generators. Start-up of the main engines, load testing of the parking and emergency diesel generators, commissioning of boilers designed to heat the vessel - the final stage of the Elbrus mooring tests, taking place at the outfitting embankment of the Northern Shipyard. After finishing mooring, the ship will go to factory sea trials.

Elbrus has significant technical advantages over other supply vessels. The total power of the main diesel generators (18,400 kW) will allow it to transport 2 thousand tons of payload in clear water at a speed of at least 18 knots, and the ice class (ARC4) will allow it to sail in the Arctic seas all year round.

"Elbrus" corresponds to automation class A1, which means that the vessel can be serviced by a minimum number of personnel. Elbrus has increased maneuverability thanks to bow thrusters, which will allow it to deliver cargo to ships on the high seas and in harbors, where ships used today navy, they can’t come in. High productivity of loading and unloading operations on board will be ensured by electro-hydraulic cranes with a lifting capacity of 50 tons. On operating ships there are quite a few cranes with such a large lifting capacity.

"Elbrus" is capable of not only transporting and reloading dry cargo, it has the functions of a tugboat and rescuer, and can help ships and vessels in distress. For this purpose, it provides premises for temporary accommodation of 28 people.

In the next two weeks, the crew will move onto the ship to participate in mooring operations together with the shipbuilders and prepare for factory sea trials.

Elbrus, the lead ship in a series of three logistics support vessels, was laid down in 2012. Two other vessels, Vsevolod Bobrov and Kapitan Shevchenko, were laid down in 2013 and 2014, respectively. Project 23120 was developed by the St. Petersburg design bureau “Spetssudoproekt”.

The Severnaya Verf shipyard (part of JSC USC) will conduct the first stage of factory sea trials of the lead logistics support vessel of Project 23120 Elbrus within seven days.

The entire program of factory sea trials (FST) is divided into three stages. During the first, seven-day stage, under the conditions of a real sea passage, a commissioning team of about a hundred specialists will test all equipment and systems and check the main power plant in different operating modes.

After the vessel returns to the outfitting quay, the shipbuilders will complete mooring tests and eliminate any identified deficiencies. Next, the ship will enter the second, main stage of chemical testing, combined with state tests. It is designed for 14 days. During this time, all equipment and systems will be checked and presented to the customer and the Russian Maritime Register of Shipping in the scope of sea trial programs and methods.

Upon completion of the second stage, the shipbuilders will inspect the equipment and systems, prepare the vessel for towing to its home base, where the vessel will be handed over to the customer and a flag-raising ceremony will take place. The shipbuilders plan to transfer the vessel to the Ministry of Defense by the end of 2016.

"Elbrus" has significant technical advantages over other logistics support vessels, since its design was based on the principle of versatility - the ability to perform a wide range of tasks.

The total power of the main diesel generators (17.8 thousand kW) will allow it to transport 4.5 thousand tons of payload or up to 40 sea containers in clear water at a speed of at least 18 knots, and the ice class (ARC4) will allow it to sail in Arctic latitudes, overcoming ice thickness of 0.6 m at a speed of 2 knots. In addition, due to the powerful power plant, the ship can follow in the formation of ships performing a combat mission.

Elbrus has increased maneuverability thanks to bow thrusters, which will allow it to deliver cargo to ships on the high seas. High productivity of loading and unloading operations on board will be ensured by electro-hydraulic cranes with a lifting capacity of 50 tons. On operating ships there are quite a few cranes with such a large lifting capacity. Maneuverability and equipment with modern powerful cranes make the Project 23120 vessel an excellent assistant in servicing drilling platforms. The vessel has the ability to receive and transfer cargo from a helicopter.

"Elbrus" is capable of not only transporting and reloading dry cargo, it has the functions of a tug. For towing support, main and auxiliary towing winches with a traction force of 120 and 25 tons, respectively, are installed on the deck. This equipment in combination with a powerful power plant, it allows, if necessary, to tow even an aircraft carrier.

Another purpose of the vessel is to help ships and vessels in distress. For this purpose, it is equipped with a pressure chamber for decompression and general barogen therapy and a rescue evacuation system, as well as premises for temporary accommodation of 16 people.

"Elbrus" is ready to carry out research tasks. For example, to map the bottom topography and search for sunken objects, it is equipped with a multi-beam echo sounder.

"Elbrus" corresponds to automation class A1, which means that the vessel can be serviced by a minimum number of personnel. The crew has comfortable cabins, a modern utility block, a gym, and a sauna with a swimming pool.

During the construction of Elbrus, import substitution of some equipment was successfully carried out. For example, instead of an imported power cable, a domestic analogue was used, a foreign finely sprayed water system was replaced with a Russian one, just as instead of a European-made hydroacoustic antenna, one made in Russia was used.

Elbrus, the lead logistics support vessel of Project 23120, was laid down in 2012. Project 23120 was developed by the St. Petersburg design bureau “Spetssudoproekt”.

Main characteristics of the vessel:
length - 95 m;
width - 22 m;
draft - 9 m;
speed – 18 knots
displacement - 9,500 tons;
cruising range - 5,000 nautical miles;
autonomy - about 60 days;
crew - 27 people.

http://www.korabel.ru/news/comments/severnaya_verf_nachala_zavodskie_hodovye_ispytaniya_sudna_tylovogo_obespecheniya_elbrus.html

READ ALSO:

  • Vyborg Shipyard is provided with orders...
  • The 1st stage of the factory chassis has been successfully completed...
  • Severnaya Verf launched a ship...
  • Sea trials have begun at the Caspian Flotilla...
In St. Petersburg, at the Severnaya Verf shipbuilding enterprise, at this very moment the lead logistics support vessel of Project 23120 Elbrus is undergoing mooring tests. I, along with Defend Russia correspondent Anastasia Voskresenskaya, boarded the ship to find out all the details about Elbrus and photograph all possible details.

Severnaya Verf is 103 years old, and over its long life the plant has built about 600 ships and vessels. The shipyard is interesting because it was, to some extent, an experimental testing ground: everything here was created according to the principle of the Guinness Book of Records - “the largest”, “the fastest”. Now the plant builds both military and civilian ships, including logistics support vessels.

2.

One of them, namely the lead logistics support vessel of project 23120 Elbrus, is currently undergoing outfitting work and mooring tests. Project 23120 was developed by the St. Petersburg design bureau "Spetssudoproekt", and the ship itself was laid down at the Severnaya Verf shipyard in 2012.

3. Shall we go inside? Let's put on our helmets and go :)

4.

5.

"Elbrus" is designed for loading, storing, transporting and transferring cargo ashore and to ships, as well as for towing support, providing assistance to the crews of ships and vessels in distress.

6.

Now, as part of the completion, the sewing and installation of equipment in residential and service areas, commissioning work on various units and devices are being carried out, installation and hydraulic tests of general ship systems and power plant systems are being carried out.

7.

The premises themselves inside the ship are already completely ready. On at the moment Furniture is being installed and fastened at Elbrus. The furniture on the ship will be very good.

8.

9.

As for mooring tests, they include: testing electrical equipment, checking the operation of towing, cargo and mooring devices, communications and navigation equipment. Now the shipbuilders are preparing to check the main power plant and start up diesel generators and the systems that serve them.

10.

At this stage, shipbuilders check all systems of the vessel under construction using more than 120 mooring test methods.

11.

Work on Elbrus is progressing actively. Shipwrights work overtime.

12.

To resolve all current issues, a temporary office was equipped at Elbrus. There are meetings here where builders communicate with the designer, and there is also an in-plant telephone. For now, the ship receives shore-based electricity, and after the launch of diesel engines, it will switch to its own, ship-based electricity.

13.

Tests of the emergency diesel generator have already been completed, and the standby diesel generator has been started. It was thanks to them and controlled propulsion systems - rudder propellers - that Elbrus, in comparison with ships with conventional propulsion systems, received better maneuverability both in course and speed. The ships of this project can, according to shipbuilders, spin around their axis like a tractor. This means they can moor for cargo delivery at any time and from any angle. In addition, this technical solution made it possible to reduce the volume of the engine room, increasing cargo capacity.

14.

The main characteristics of Project 23120 logistics support vessels are as follows: length - about 95 meters, width - about 22 meters, displacement - approximately 10,000 tons, cruising range - about 5,000 miles, autonomy - about 60 days. The ship is designed for 27 crew members, but in the event of rescue operations, the number of people on board the Elbrus can be increased to 43. For comparison, this is ten times less than the number of people building the ship now. By the way, in the room intended for the rescued, the same shipwrights’ office is now located.

15.

As for cargo delivery, Elbrus can transport about forty twenty-foot containers or, conversely, twenty forty-foot ones. All containers are placed on the cargo deck. Contents - everything that fits into the container. But no liquids, only dry cargo. For loading and unloading containers on the Elbrus there are two symmetrically located cranes of 50 tons each. (Photo No. 6)

16.

"Elbrus" has a high ice class ARC4, which gives it the opportunity to sail in Arctic latitudes. The vessel's hull thickness has been increased and a double side is used. That is, there is an air gap between the walls. This is especially true for those compartments where water and fuel tanks are located.

17.

18.

The cabins on Elbrus are single and double. In the latter, the beds are arranged in two tiers. There is a bathroom in every cabin.

19.

The ship uses several types of insulation, including liquid insulation - "Teplotor". A layer of 3 mm replaces the usual glass wool, 6-7 centimeters thick. So, in addition to convenient application, Teplotor’s big advantage is also its space saving. This is especially true where a wide viewing angle from the window is important, as, for example, on the captain's bridge. In Arctic conditions, this isolation also worked well. Otherwise, according to the ship's builders, it would not have been used.

A series of three logistics support vessels with a high ice class ARC4 based on Project 23120 is being built at the Severnaya Verf Shipyard OJSC for the Ministry of Defense of the Russian Federation in accordance with the contract dated June 29, 2012, concluded between the Severnaya Verf Shipyard OJSC and the Federal Agency for the supply of weapons, military.

The contract provides for the construction of the lead vessel and two serial ones. The lead vessel should be delivered to the customer in November 2014, the second - in November 2015, the third - in November 2016. Vessels based on Project 23120 will be built for the Northern, Black Sea and Pacific fleets. The vessels have a high ice class - ARC4, that is, they have the ability to sail year-round in the Arctic seas.

The cost of building a series of ships is 11.715 billion rubles, the cost of building the lead ship is 3.9 billion rubles.

The designer of ships based on project 23120 is Spetssudoproekt CJSC (St. Petersburg).

Architectural and structural type: marine, steel, single-deck vessel with rudder propellers, a deckhouse in the bow, with a free deck area in the stern, a double bottom and double sides, bow thrusters and a towing winch.

Basic technical specifications ships based on project 23120: Total displacement 9000 tons, deadweight 3600 tons. Maximum length 90.0 meters, maximum beam 22 meters, draft 8.65 meters. The speed in clear water is at least 18 knots, in flat ice 0.6 meters thick it is about 2 knots. The total power of the main diesel generators is 15,000 kW. Cruising range 5000 miles. Autonomy (in terms of provisions) is about 60 days. The crew consists of 27 people. The ship has equipped places and premises for temporary accommodation of about 50 rescued people.

The vessel is equipped with electro-hydraulic cranes with a lifting capacity of 50 tons in the cargo deck area on each side to ensure loading and unloading of cargo, as well as performing auxiliary work. Cranes provide cargo operations throughout the entire cargo deck area.

Designed for loading, storing, transporting and transferring dry cargo to the shore and various ships, as well as for towing support, providing assistance to the crews of ships and vessels in distress.

Navigation area: independent navigation without area restrictions in non-Arctic seas; independent sailing during summer-autumn navigation in the Barents Sea; sailing under escort behind an icebreaker during winter-spring navigation in the Barents Sea.

Lead logistics support vessel "Elbrus" of project 23120 (serial number 880): November 14, 2012 - the day when Severnaya Verf solemnly celebrated the centenary of its founding. By order of the Commander-in-Chief of the Navy, Admiral Viktor Chirkov, No. 657 dated October 31, 2012, the name “Elbrus” was assigned. As reported on November 28, 2014, in the first half of 2015. Designed for the Northern Fleet. May 18, 2015. June 26. According to the message dated October 12, it is 88%. According to the message dated November 2, mooring tests. On December 29, during outfitting work, smoke appeared in the pump room. The incident will not affect the delivery date. According to a message dated March 18, 2016, outfitting works are underway and mooring tests are underway. According to a report dated May 25, tests of the main power plant. According to a message dated September 9, the first stage of factory sea trials, which will last seven days. According to a message dated June 6, 2017, state tests are due to end in July. At the end of June from St. Petersburg to the home base - the port of Murmansk. According to a message dated July 25, for two days in the Baltic Sea to check the deviation (deviation) of the magnetic compass. According to a message dated August 2, the ship is heading to the Northern Shipyard (part of JSC USC) from the control exit to the Baltic. Shipbuilders began preparing the vessel for final tests in the northern seas. According to a message dated August 11 from the Severnaya Verf Shipyard (part of JSC USC) to the northern latitudes for the final stage of testing. According to a report dated September 20, the first half of the ship's flight test program. Will join the fleet in 2017. According to a message dated November 1, the Northern Fleet is completing tests and preparing for the transfer procedure. On April 2, 2018, the leadership of the Russian Navy approved the acceptance certificate of the state commission on the completion of state tests of the vessel. On April 9, the flag of the Navy Auxiliary Fleet was raised on the ship. The vessel is included in the detachment of support vessels for the auxiliary fleet service of the joint strategic command of the Northern Fleet.

Class symbol designations KM✪ Arc4 AUT1 DYNPOS-2 BWM(E-S) supply vessel:

KM✪ – a self-propelled vessel built according to the rules of the Register and certified by the Register;

Arc4 - sailing in the Arctic seas is allowed during the winter navigation period in thin first-year ice, during the summer-autumn period - on average first-year ice up to 0.9 m thick. Areas and operating conditions are limited;

The vessel meets the applicable requirements of Part V “Division into compartments” of the Rules for the Classification and Construction of Sea Vessels and fully complies with the requirements of Section. 3 of the specified part of the Rules in case of flooding of one compartment along the entire length of the vessel with estimated damage to the side;

AUT1 - the scope of automation allows the operation of the ship's mechanical installation without the constant presence of maintenance personnel in the machine rooms and in the central control room (CCU);

DYNPOS-2 - class 2 dynamic positioning system has redundancy, which ensures that the vessel remains above the positioning point in the event of a single failure in any active element of the system. It is understood that failure in any passive element of the system is excluded due to the availability of appropriate protection against mechanical damage and the properties of the element, confirmed by the Register certificate;

BWM(E-S) - the vessel carries out ballast water management through at-sea ballast exchange and, accordingly, is equipped with a ship's Guide for Safe At-Sea Ballast Exchange, approved by the Register. As a method of ballast water management, ballast replacement at sea using the sequential replacement method was chosen;

supply vessel - support vessel.

The first serial logistics support vessel (former "MB-75") of project 23120, construction number 881: December 19, 2013. Must be transferred to the customer by the end of 2016.

The second serial logistics support vessel "Captain Shevchenko" of project 23120, construction number 882: The keel was laid on July 24, 2014. Must be transferred to the customer by the end of 2016.

According to a message dated May 27, 2018, the ship is preparing for the annual joint Russian-Norwegian exercise “Barents 2018”, which will take place from May 29 to May 30 in the water area Barents Sea under the leadership of Norway. On May 31, to the main base of the Northern Fleet - the city of Severomorsk, after the completion of the international exercise "Barents 2018". On August 19, as part of the naval demining detachment of the Northern Fleet to carry out work to search, detect and destroy explosive objects in the waters of the Ob Bay of the Kara Sea. October 01 to Murmansk after successfully completing the assigned tasks in the waters of the Ob Bay and the Yenisei Bay of the Kara Sea.

On February 26, 2019, as part of a detachment of ships of the Northern Fleet in the Barents Sea, he headed for the Atlantic. On March 20, the ships moved from the Mediterranean to the Red Sea through the Suez Canal. April 23 at ceremonial events dedicated to the 70th anniversary naval forces People's Liberation Army of China. According to a report dated April 26, the visit to the People's Republic of China and left the port of Qingdao to the Yellow Sea. On May 10, Vladivostok, where a detachment of ships celebrated Great Victory Day and took part in ceremonial events. On June 11, a business call at the port of Puerto Bolivar of the Republic of Ecuador on west coast South America, which is June 13. According to a message dated June 19 to the passage of the Panama Canal. On July 08, a business call to the port of Praia in the Republic of Cape Verde and continued to carry out tasks according to the long-distance voyage plan.

As reported, on September 8, 2016, factory sea trials began in the Baltic Sea of ​​the lead sea tug built for the Russian Navy at the Severnaya Verf Shipyard in St. Petersburg "Elbrus"(serial number 880) project 23120 (code "Longvinik").

The lead sea tug built for the Russian Navy at the Severnaya Verf Shipyard OJSC
"Elbrus"Project 23120 returns from its first start to factory sea trials. St. Petersburg, 09.14.2016 (c) RussianArms

"Elbrus" became the lead ship built in accordance with a contract worth 11.715 billion rubles for the construction of a series of three Project 23120 naval logistics support vessels for the Russian Ministry of Defense, signed on June 29, 2012 between the Severnaya Verf Shipyard OJSC and the Federal Agency for the Supply of Arms , military, special equipment (Rosoboronpostavka). According to the terms of the contract, the first vessel was to be delivered to the customer by November 25, 2014 (delivery to the Northern Fleet), the second - by November 25, 2015 (delivery to the Black Sea Fleet), the third - by 25 November 2016 (delivery to Pacific Fleet), however, in 2013, the terms of the contract were postponed to a year later.

Groundbreaking ceremony"Elbrus" at the Severnaya Verf on November 14, 2012 on the day of the centenary of the Severnaya Verf. In the summer of 2013, by order of the Commander-in-Chief of the Russian Navy, Project 23120 vessels were reclassified into sea tugs (according to unofficial information, this was done to reduce staffing table ships). As a result, Project 23120 vessels became the largest tugs in history Russian Navy. On December 19, 2013 took place for the Russian Navy "Severnaya Verf" the second unit of project 23120, already called a sea tugMB-75(in February 2015 renamed to"Vsevolod Bobrov";serial number 881). On July 24, 2014 took place third unit of project 23120"Captain Shevchenko"(serial number 882), which was again considered a maritime logistics support vessel.

"Elbrus" was from the Severnaya Verf workshop on May 18, 2015 and launched on June 26, 2015. However, completion of the vessel afloat took more than a year, which was reported to be due to the non-delivery of some Western equipment due to sanctions. As a result, the lead vessel of Project 23120 will apparently be delivered two years behind schedule.

Project 23120 vessels were designed by St. Petersburg JSC Spetssudoproekt under the leadership of chief designer Anatoly Petrov and are built to the class of the Russian Maritime Register of Shipping (RS): KM Arc4 AUT 1 DYNPOS-2 BWM (E-S) Supply vessel. In fact, the vessel is a military version of standard offshore supply and support vessels for offshore oil and gas production. The project 23120 vessel is designed for loading, storing, transporting and transferring dry cargo to shore, surface ships, submarines and ships, as well as for towing support and assistance to the crews of ships and vessels in distress.

The total displacement of the project 23120 vessel with a draft of 8.5 m is about 9000 tons, the deadweight of the vessel with a draft of 8.5 m is about 3600 tons. The length is 90.0 m, width - 22.0 m, maximum draft - 8.65 m The specific speed of the vessel when fully loaded at maximum draft and waves up to three points on the Beaufort scale, with a total power of the main diesel generators of 15,000 kW, is at least 18 knots. Provision is made for accommodation of a crew of 27 people.