The Project 11661K missile ship Tatarstan is the flagship of the Caspian Flotilla of the Russian Navy. The ship was built according to the project 11661K at the Zelenodolsk shipyard named after V.I. Gorky as a patrol ship and is the lead in a series of two ships of this project... The second ship of this project is "Dagestan".

The missile ship "Tatarstan" was laid down in May 1990 as a patrol ship "SKR-200", building number 951. In 1993 it was launched. By 1995, it was almost ready, however, due to the cessation of funding, its completion was frozen (from 1994 to 1996). On October 03, 1996 it was renamed "Tatarstan". It entered service on August 31, 2003. Also in 2003, the ships of the 11661K project were reclassified as rocket ships. Board number 691 (since 2003).

The missile ship "Tatarstan" is designed to search for and combat underwater, surface and air targets, carry out patrol service, conduct convoy operations, as well as protect the maritime economic zone. Equipped with artillery, anti-ship, anti-aircraft and anti-submarine weapons.

Main characteristics: Displacement standard 1500 tons, full 1930 tons. Length 102.2 meters, width 13.76 meters, draft 3.7 meters. Full speed 28 knots. Cruising range 3800 miles at 14 knots, 950 miles at 27 knots. Swimming autonomy 15 days.

Powerplant: 1 x 38,000 hp DGTA M-44 (2 x 15000 HP GTU, 1 x 8000 HP 86B diesel), 2 fixed pitch propellers.

Armament:

Navigation armament: navigation radar MR-212 "Vaigach".

Radar weapons: RLK 34K1 "Monolith" or "Mineral-M"; Radar MR-352 "Positive (-M1)"; MPZ-301 "Baza" (SAM); MSA MR-123 "Vympel".

Electronic weapons: 2 × PU complex REP PK-16 or 4 × PU complex REP PK-10 system REB TK-25 (E); BIUS "Sigma" ("Sigma-E");

GAS "Zarnitsa" or GAK MGK-335.

Artillery: 1 × 76 mm AU AK-176M; 2 × 14.5 mm MTPU.

Anti-aircraft artillery: 2 × 30 mm AU AK-630M.

Missile armament: 2 × 4 PU SCRC "Uranus"; 1 × SAM "Osa-MA-2"; 2 × Igla-M MANPADS.

In 2007, under the flag of the commander of the flotilla, he made a call at the port of Anzali, Iran.

On September 20, 2012, the Caspian Flotilla's naval strike group consisting of missile ships Dagestan, Tatarstan, missile boats Budennovsk and Borovsk successfully launched missiles at coastal and surface targets at one of the sea ranges in the northern part of the Caspian Sea. According to a report dated September 28, on the ships of the Caspian Flotilla in the bases of Astrakhan and Makhachkala for air defense. October 09 within the framework of strengthening and developing cooperation between the fleets of the two countries in the Caspian Sea. According to the message of October 3 of the Republic of Kazakhstan, the operational groups of the headquarters of the flotilla and the naval base of the Navy of the Republic of Kazakhstan conducted a joint command-staff exercise. According to a message dated October 16, as part of the flagship - the missile ship "Tatarstan" and sea ​​tug"MB-58" returned to the point of permanent deployment after carrying out a collection-cruise to the central and southern parts of the Caspian Sea.

February 05, 2013 on the flagship of the Caspian flotilla rocket ship "Tatarstan" under the leadership of the flotilla commander Vice-Admiral Sergei Alyokminsky special course task. On March 11, as part of the flagship of the association, the missile ship "Tatarstan", missile boats "Budennovsk" and "Borovsk" sailed into the Caspian Sea to conduct combat training events. According to a report dated March 18, the Caspian Flotilla began preparing ship detachments for cruises to the ports of neighboring countries. The detachments will include missile ships "Dagestan" and "Tatarstan", small artillery ships, as well as support ships. According to a report dated April 16, about 1000 people and 30 ships, landing boats and support vessels of the Caspian Flotilla, including the missile ships "Dagestan" and "Tatarstan", as well as small artillery ships "Astrakhan" and "Volgodonsk", which passes in the northern parts of the Caspian Sea. On April 23, a detachment of warships of the Caspian Flotilla consisting of the KFL flagship of the patrol ship "Tatarstan" and the missile ship "Dagestan" fought a sea battle with the ships of the imaginary enemy, in the role of which were the small artillery ships "Astrakhan" and "Volgodonsk". According to a report dated April 29, the crew of the flagship of the Caspian flotilla of the missile ship "Tatarstan" with combat missile firing at a sea target. On June 7, the crew of the flagship of the Caspian flotilla of the rocket ship "Tatarstan" with live fire in the Caspian sea ranges. According to the message of August 16 on the drawing of the oncoming sea battle between the detachments of ships.

According to a report dated January 10, 2014, air defense (AD) exercises were held in Astrakhan and Makhachkala, in which more than 10 surface ships and boats of the flotilla, including the missile ships "Tatarstan" and "Dagestan",. On March 15, a grouping of the Caspian Flotilla of the Southern Military District consisting of missile ships Tatarstan and Dagestan, a medium landing boat Ataman Platov and four high-speed landing boats of the Serna type exercises. According to a report dated April 22, the Caspian flotilla of the coastal missile division and the missile ship (RK) "Tatarstan". On May 05, they left the basing points of Makhachkala and Astrakhan and began to conduct a bilateral test tactical exercise in the Caspian Sea, in which about 20 warships and support vessels are involved, including the missile ships Dagestan and Tatarstan, small missile ships and , small artillery ships "Volgodonsk" and "Makhachkala".

In September 2014, he started modernization, which will be carried out by the Astrakhan branch of the Zvezdochka Ship Repair Center.

According to the message dated May 20, 2015 on the use of the new Hals radar station (radar) installed on the ship as part of the modernization and scheduled repair of its systems and mechanisms. The installation of the Hals radar can significantly improve the characteristics and combat capabilities of radio equipment for detecting air and surface targets. V automatic mode it detects and determines the elements of the target's movement (course, speed) and issues recommendations for performing a maneuver to deviate from the surface object. Also, the ergonomic characteristics of the workplaces of operators of combat posts (place of service and performance of combat training tasks by personnel) have also improved due to the use and installation of modern materials and equipment. Replaced by modern equipment systems for target detection and tracking of the surface situation, jamming, electronic suppression and ship warfare. Improved and automated home power plant and the electric power plant of the ship (mechanisms that ensure its movement, maneuvering and crew life) in terms of increasing resource indicators and reliability. The modernization and repair of the ship is planned to be completed in the fall of 2015, after which the crew will begin to perform the tasks in accordance with their intended purpose. According to a report dated June 12, on air defense with the repulsion of enemy air strikes.

According to a message dated January 4, 2016, for the modernization, which is carried out by the Astrakhan branch of the Zvezdochka Ship Repair Center. The modernization and repair of the flagship is planned to be completed in the fall of this year. During the modernization, it will be installed new system navigation and weapon control. According to the message of May 12, the Astrakhan branch of the Zvezdochka Ship Repair Center began moving to the permanent base - Makhachkala after the completion of the repair and modernization. According to a report dated June 2, he began to carry out daily activities at the base and to prepare the ship for a campaign and battle as part of solving the elements of the first course task K-1. According to a report dated July 20, the port of Makhachkala was based and began practicing combat training measures in the Caspian Sea ranges. According to a message dated October 18, as part of a detachment of the Caspian Flotilla on an unofficial visit to the port of Bandar-Anzali, Islamic Republic of Iran. According to the message of October 24, a friendly visit to the port of Aktau in Kazakhstan as part of the detachment of the Caspian Flotilla. According to a message dated October 27 to the port of Makhachkala.

According to a report dated January 30, 2017, on the ship, demonstration classes on working out the elements of the course task K-1. According to a report dated March 21, the basing point began to carry out training and combat missions in the naval training grounds of the association.

According to a message dated March 12, 2018 from a permanent deployment point in Dagestan to carry out artillery and anti-aircraft artillery fire at sea. According to a report dated March 15 at the point of permanent deployment after the successful execution of artillery and anti-aircraft artillery firing at sea.

The patrol ships of project 11661 are designed to perform complex tasks in the search and elimination of underwater, surface and air targets, in carrying out combat service, in escorting, as well as in protecting maritime economic zones. They are equipped with artillery, anti-ship, anti-aircraft and anti-submarine weapons.

A little from the history of the creation of ships of the project 11661

Patrol ships (corvettes) and rocket ships began to be developed in the early eighties. The development was carried out by the Zelenodolsk Design Bureau. The development of anti-submarine ships for coastal zones was carried out as the development of another project 1124M - a small anti-submarine ship, with "Livn" - an anti-submarine missile cruiser... Then they developed two versions of tactical and technical assignments, and a year later they proposed both versions of draft designs - an anti-submarine ship with a PLRK in accordance with project 1124M and an anti-submarine ship with a displacement of up to two thousand tons with more significant efficiency.

In the same year, following changes in claims by Navy to the project, the second project was assigned the number 11660 (and the export version - 11660E) and reclassified into a patrol ship. The analysis of research in the projects showed that it was possible to hand over the "watchdog" in the export version as early as 1990, while the Soviet version could have been handed over no earlier than two years later.

Back in the mid-eighties, a requirement was put forward to equip patrol ships (TFR) with Uranus anti-ship missile complexes, which were planned to be developed in 1987. According to the December Decree of the Council of Ministers of the USSR in 1984, it was decided to develop patrol ships according to project 11661. Draft projects 11661 with CODOG propulsion systems were completed a year later.

By the beginning of 1986, the technical design of patrol ships under project 11661 was completed. Later, it was decided to unify the ships of projects 11660 and 11661 by eighty-five percent, start work and rearrange them in a single structural platform with various weapons, differences in engines and equipment.

In September 1986, they began to defend project 11661. Following the modifications for Uranus and Zarya and other equipment, they formulated the concept of the Basic Platform for Ship Families in the final version. To test the shape of the hulls and the effect of the radomes of the antennas to determine the seaworthiness, a ship model was created and tested. The technical project of the 11661 project was approved a year later.

Then they set the task to unify projects 11660 and 11661. Using the concept of the "Basic platform" Zelenodolsk Design Bureau began to produce working design documentation for project 11661, as well as develop technical projects for project 11660.

After all the agreements and approvals, the ships were laid. And already in 1993, the lead ship of Project 11661 was destined to go down to the water with the beginning of its completion. At the beginning of 1995, a crew appeared in Zelenodolsk to master the patrol ship. In the same year, several ships were refused from a foreign customer (according to some Indian sources), and all work on their construction was stopped.

In addition, in the same year, the construction of the ship was stopped with ninety-three percent readiness. The crew was disbanded, the ship was mothballed due to underfunding, as well as due to the fact that the customer himself (the Russian Navy) was not fully determined on different types patrol ships.

However, in the period 1995-1998 Zelenodolsk Design Bureau developed export projects "Gepard" and "Gepard-3.9" for a foreign customer.

In 2001, the leadership of the Navy decided to complete the construction of one of the ships under the project 11661K, which was supposed to enter the Caspian flotilla with the name "Tatarstan". The ship lost its anti-submarine weapons. On it, the project was adjusted to meet all the requirements. In April 2002, a crew appeared in Zelenodolsk to take possession of the new ship.

At the same time, they carried out inclining with the ship and found out that the displacement deviated from the calculations by up to one ton. In July 2002, "Tatarstan" managed to successfully leave Zelenodolsk Shipyard in order to go to the Makhachkala region to carry out test activities. The sea test passed with a five-point excitement. As a result, the ship was adopted by the Russian Navy, and the Caspian Flotilla acquired its own flagship in August 2003.

The predecessors of the "Cheetahs"

The predecessors of the Cheetahs were the Albatrosses, which turned out to be small anti-submarine ships under the project 1124 with the NATO code designation - "Grisha class corvette". They were built in 1970-1980 for the Soviet Naval Forces, which include two main series of projects 1124 and 1124M.

Samples of project 11661 - "Tatarstan" and "Dagestan"

The firstborn in Project 11661K was the ship already known as Tatarstan, which entered service in August 2003. He was subsequently sent to the Caspian Flotilla as its flagship.

The second patrol ship happened to be "Dagestan". Its delivery to the Navy was originally planned for the first half of 2012. However, it was postponed due to the seriousness of the damage received back in January of the same year during the Black Sea mooring tests near the city of Novorossiysk. After restoration and repair measures, "Dagestan" managed to reach the Caspian Sea to participate in the second stage in the state tests for the implementation of missile firing at coastal targets "Kalibrom-NK".

Participation in the shooting at a distance of one hundred nautical miles was carried out safely. The patrol ship "Dagestan" also had to take part in the parade on the Day of the Russian Navy in the city of Astrakhan. In the autumn of the same year, he was involved in the Kavkaz-2012 maneuvers, in their naval unit.

However, three years later the whole world learned about "Dagestan". So, in October 2019, at night, a naval strike group in the Caspian Sea carried out a massive strike using cruise missiles. The strike was inflicted by the "Caliber NK" complex sea-based on the infrastructure of ISIS in Syria. The Dagestan was also composed of six ships.

Housings

Ship hulls are ten watertight compartments. The material for their execution was low-alloy steel, and for the superstructure blocks - aluminum-magnesium alloy, resistant to marine environments. In the event of flooding of two adjacent compartments, the ship will remain afloat, having a course with the preservation of combat effectiveness.

Power plant and running properties

The main power plant is the twin-shaft CODOG. With a medium-speed diesel engine 61D with a power of 8000 horsepower, using a complex gearbox, it is provided with all cruising modes, and with the help of two gas turbines with a total power of 29000 horsepower, the ship's full speed up to 28 knots is provided. The electrical installation consists of three diesel generators, 600 kW each.

The crew of the patrol ship is 121 military personnel, of which 15 are officers.

Armament of the ships "Tatarstan" and "Dagestan"

The ships under the project 11661 have powerful missile, anti-aircraft missile and artillery weapons. The main weapon of "Tatarstan" is "Uranus". This is a strike complex with Kh-35 anti-ship cruise missiles, with a firing range of up to one hundred and thirty kilometers.

The "Dagestan" is armed with a universal missile system- "Caliber-NK", which can use high-precision cruise missiles of several types. They hit surface and coastal targets with a range of up to three hundred kilometers. From artillery weapons - 76.2-mm artillery complex AK-176M and 30-mm automated twin artillery mount AK-630M, which ensure the defeat of sea, ground and low-flying air targets.

Frigates "Gepard-3.9" - ships of a new generation

Frigates of the "Gepard-3.9" class are ships of a new generation. They were developed by Zelenodolsk Design Bureau with an existing universal base platform. The prototype for "Gepardov -3.9" was a missile ship named "Tatarstan" from project 11611, and "Dagestan" is the second such built domestic missile ship, a version corrected at the insistence of the customer in the project 11611K.

The construction of frigates for the Vietnamese customer is still carried out according to established requirements The Naval Forces of this state. With a total displacement of up to 2,100 tons, they have a length of 102 meters, a width of just over 13 meters, and a draft of just over 5 meters. The ships have a combined diesel-gas turbine power plant (in accordance with the CODOG scheme).

With this power plant, ships develop a speed at full speed of up to 28 knots, and an economic ten-knot speed allows frigates to sail at ranges of up to 5,000 nautical miles. Autonomous sailing is twenty days. Well placed residential and office space, the presence of a system that conditions the air and maintains the necessary conditions microclimate will contribute to good conditions habitability, which is simply vital in tropical climates.

"Cheetah-3.9" are multipurpose ships designed for patrolling in territorial waters and exclusive economic zones, striking enemy surface targets, providing fire support for airborne units, to provide anti-aircraft and anti-submarine defense in convoy activities.

As a result, their weapons are diverse and well balanced. These include the Urany-E anti-ship missile systems, the AK-176M universal 76.2-mm artillery mounts, and the small-caliber anti-aircraft system. Control over the control of all these weapons is carried out by the responsible high standards of our time, the combat information and control system "Sigma-E". The stern of the ship has a helipad for takeoff and landing. In addition, the helicopter has a special shelter - a hangar, which will protect it from sea winds and waves.

Soon "Cheetahs" will make the transition to the Baltic Sea, where they will be tested. Implementation of the contractual part for the construction of patrol ships for a Vietnamese customer can change the correlation of the ships produced by the enterprise. So, about forty percent will go to the military and sixty percent to civilian products(before, 30% went to military products and 70% to civilian products).

In the presence of the base platform "Cheetah", you can not be limited to the construction of only multipurpose ships, but you can also build ships with reinforced shock, anti-submarine and anti-aircraft missiles, with a wide variety of power plants and electronic equipment. With the help of the same platform, ZPKB developed a modification of ships for patrolling on the high seas, which have a greater autonomy of navigation. It should be especially noted that the family of "Cheetah" is relatively inexpensive in relation to similar ships of foreign buildings.

Cheetah-5.3 - frigates based on patrol ships of project 11661

Purpose

"Cheetah-5.3" are frigates designed for:

  • Defeat air, surface and submarine enemy;
  • Execution of tasks while escorting;
  • Conducting service and combat activities on patrol;
  • Fire support for landing units;
  • Installation of minefields;
  • Tasks for the protection and patrolling of maritime state borders and economic zones;
  • Maintaining maritime operations;
  • Demonstration of the flag in areas that represent national interests.

Frigates are capable of dealing with a wide range of tasks, both independently and as part of tactical groups.

Armament "Cheetah"

Strike missile armament

In order to eliminate surface objects, the ships have at their disposal the Uran-E anti-ship missile system and four deck-mounted inclined launchers of four missiles each, as well as a ship-based firing control system.

Artillery armament

Complementing the artillery weapons of the frigate of the project "Cheetah 5.1", "Cheetah 5.3" have two missile and artillery complexes "Palma" and anti-aircraft guided missiles "Sosna-R".

Anti-submarine and mine weapons

Antisubmarine and mine armament "Cheetah" is expressed:

  • Two twin-tube rotary torpedo tubes DTA-53 of 533 mm caliber;
  • RPK-8E anti-submarine reactive complex;
  • A set of instruments for controlling the "Blizzard" - anti-submarine weapons.

During peacetime, ships are equipped with search and rescue versions of Ka-28 or Ka-31 helicopters, and during wartime anti-submarine options.

Power plant

The main power plant is a two-shaft diesel unit with adjustable pitch propellers, made according to CODAD schemes. The main power plant includes four diesels with a capacity of 4700 horsepower, but can have two diesels with a capacity of 6494 horsepower and two diesels with a capacity of 2425 3298 horsepower, two gearboxes and a local protection and control system.

If you have any questions - leave them in the comments below the article. We or our visitors will be happy to answer them.

Patrol ships of the project 11661 (code "Gepard", according to NATO codification - Gepard)- a type of patrol ships of the Russian and Vietnamese fleets. Ships of the series are being built at the Zelenodolsk plant named after A.M. Gorky since 1990.

In the early 1980s, it became necessary to develop a new coastal patrol ship. It was supposed to replace the ships of Project 1124. This was due to the change in the purpose of the patrol ships of Project 11540, which in the final version were supposed to replace the larger patrol ships of Project 1135. The Zelenodolsk Design Bureau headed by chief designer Yu.A. Nikolsky, and then V.N. Kashkin.



Due to the requirements of the Navy for the placement of a powerful sonar station, the ship's displacement increased to 2000 tons, which became close to the ships of the competing project 12441. Those were more powerful anti-ship missiles and the presence of a helipad.

At the end of 1990, the lead ship of Project 11660 was laid down, which was named Burevestnik, but after a while its construction was stopped. In 1995, its construction was discontinued and the ship was mothballed. The ship was later dismantled.

The second ship was laid down in 1993 under the export project 11661 for the Indian Navy, but in 1995, when it was almost ready, funding stopped. Later, it was completed according to the project 11661K, adjusted for the Russian Navy, and launched under the name "Tatarstan"; it entered service on August 31, 2003 and became the flagship of the Caspian Flotilla.

The third TFR was also founded according to the 11661K project in 1991 and was named "Dagestan". Its delivery to the fleet was originally planned for the first half of 2012, but was postponed due to damage received in January 2012 during mooring trials on the Black Sea near Novorossiysk.

In July 2012, after restoration and repair work, "Dagestan" entered the Caspian Sea as part of the second stage of state tests for the implementation of missile firing at a coastal target from the "Caliber-NK" missile system. Shooting at a distance of 100 nautical miles was successful and on November 28, 2012, "Dagestan" became part of the Russian Navy.

They have a traditional flush-deck architecture with 10 watertight compartments. The ship's superstructure is made of aluminum-magnesium alloys to ensure low visibility(the so-called stealth technology).

The patrol ships of the project 11661 "Gepard" have powerful missile, anti-aircraft missile and artillery weapons. The main weapon of Project 11661E ships and the RK Tatarstan is the Uran (Uran-E) anti-ship missile system with Kh-35 (E) cruise missiles, which has a firing range of up to 130 km (up to 260 km for Uran-U) with Kh-35U missiles).

Project 11661K ship, Dagestan, is the first Russian Navy ship armed with the Kalibr-NK universal missile system, which can use several types of high-precision cruise missiles capable of striking surface, underwater and coastal targets at a distance of up to 300 km.

Artillery armament includes a 76.2 mm bow artillery mount AK-176M (ammunition - 152 rounds) and two 30 mm automated ones with ammunition of 2000 + 1000 rounds each, which ensures the fight against sea, ground and air targets. The rocket ship "Dagestan" also has two 14.5 mm naval pedestal machine gun mounts.

For air defense on the ships of projects 11660 and 11661, as well as on the Tatarstan missile complex, the Osa-MA-2 anti-aircraft missile system with an ammunition of 20 missiles is used. On the Dagestan ship, instead of the Osa-MA-2 air defense system and two AK-630s, it is installed, and on the ships of the 11661E project, its export modification, the Palma, is installed on the forecastle, with both AK-630s being installed in the stern of the superstructure side by side.

As anti-submarine weapons on the ships of pr. 11660 and 11661, two twin-tube 533 mm torpedo tubes were provided. On the ships of the 11661E project, one is used as anti-submarine and anti-torpedo weapons. It is possible to equip ships with other weapon options, including the Ka-27 ship-based anti-submarine helicopter.

V different time the ships were equipped with various radar and electronic equipment. So, the ships were installed radar complex 34K1 "Monolith", radar station general detection MR-352 "Positive", navigation radar MR-212 "Vaygach", artillery fire control system MR-123 "Vympel" and GAS "Zarnitsa". The anti-sabotage OGAS MG-757 Anapa-M is installed on the Tatarstan ship.

To control the firing of RBU on ships of pr. 11660 and 11661, PUSB "Tempest" was used, on ships of pr. 11661E, PUSB "Purga-ME" was used. Electronic warfare complex consisted of two KL-101 launchers of the REP PK-16 system or of four KT-216 launchers of the PK-10 "Brave" complex.

On the RK "Dagestan", the "Monolit" radar was replaced by "Mineral-M", and the general detection radar was replaced by "Positive-M1". Also installed hydroacoustic complex (GAK) type MGK-335, electronic warfare system TK-25 and BIUS "Sigma". Ships of the project 11661E are equipped with equipment similar to those installed on the "Dagestan" in the export version with some differences in its composition.

The main power plant is two-shaft, type CODOG. Medium-speed diesel type 61D with a capacity of 8000 hp through a complex gearbox provides all cruising modes, and two gas turbines with a total capacity of 29,000 liters. with. (one for each shaft) provide the full speed of the ship up to 28 knots. The power plant includes three diesel generators of 600 kW each.


Patrol ship / corvette / rocket ship. Development started in 1982 by Zelenodolsk Design Bureau (Zelenodolsk), chief designer - MM Nesterenko, since 1986 - VN Kashkin. The development of the anti-submarine ship of the coastal zone was carried out as a development the IPC project Project 1124M with PLRK "" since February 1982 Two variants of the tactical and technical assignment were developed and in 1983 two variants of the draft design were proposed - an anti-submarine ship with PLRK "" significantly higher efficiency. In April 1983, after changing the requirements of the Navy for the project, the second project received the number 11660 (export version - 11660E) and was reclassified in the TFR. An analysis of the development of the projects showed that the delivery of the export version of the TFR could be planned for 1990, while the readiness for the delivery of the version for the Soviet Navy in terms of weapons systems could not be earlier than 1992.


Launch of the 3M54 rocket of the Kalibr-NK missile system from the SKR pr.11661K Dagestan during the Caucasus-2012 exercise, the Caspian Sea, September 2012 (photo from Curious archive, http://forums.airbase.ru) ...



SKR pr.11661K "Tatarstan" serial number 951 at the parade on the Day of the Navy in Astrakhan, July 29, 2012 (photo - Evgeny Lukovtsev, http://ria.ru).


TFR pr.11661K "Dagestan" serial number 952 at the parade on Navy Day in Astrakhan, July 28, 2013 (http://militaryphotos.net).


In 1984, 1 Central Research Institute of the USSR Ministry of Defense put forward a requirement to equip the TFR with the Uranium anti-ship missile complex, the development of which was planned to begin in 1987. In December 1984, the USSR Council of Ministers adopted a Decree on the development of an export TFR pr.11661, TFR for the USSR Navy, pr. 11660 and PSKR pr.11662. The chief designer was appointed M.M. Nesterenko, the deputies were G.A. Zolotarev and V.V. Ivanov. Draft pr.11661 with a CODOG-type propulsion system (diesel + two gas turbine engines) was completed in early 1985. At the end of 1985, the preliminary design of the SKR pr.11660 was completed. At the beginning of 1986, the technical design of the SKR pr.11661 was completed, and during the year an addition to the draft pr.11660 was developed for the PSKR pr.11662. The USSR SMEs set the task of unifying the ships of Project 11660 and Project 1161 by 85% and began work on re-assembling projects under a single constructive platform with different weapons systems, differences in propulsion systems and equipment. In 1986, the chief designer of the project, M.M. Nesterenko, for health reasons, asked to be relieved of his post and V.N.Kashkin was appointed instead.

At the beginning of September 1986, the defense of projects 11660, 11661 and 11662 began. After modifications for the Uran missile complex, the Zarya spacecraft and other equipment, the concept of the "Basic platform for a family of ships" was finally formulated. To test the hull shape and the effect of the GAS antenna fairing on seaworthiness, a model of the SM-22 ship was created and tested (tests were carried out by V.G. Pasechnik and V.N. Aleshin). The technical project of pr.11661 and the preliminary design of pr.11660 were approved at the beginning of 1987. The task was set when developing the technical project of pr.11660 to ensure unification with pr.11661 by 80%. Using the concept of "Basic Platform" Zelenodolsk Design Bureau began to produce a working design documentation on pr.11661 and development of technical projects pr.11660 and pr.11662. At the same time, there was a release of working design documentation for Project 11540.


Model SM-22 on testing (Zelenodolsk Design Bureau. Checked by sea. 60 years 1949-2009, Kazan, Helicopter, 2009).


The creation of a reserve for the head ICR pr.11661 at Zelenodolsk Shipyard began at the end of 1987. In 1988, the technical project of pr.11661 was approved, the development of working design documentation was started, and pr.11662 is being adjusted taking into account the wishes of the USSR Border Troops. The head ICR project 1161 (factory # 951) was laid down at Zelenodolsk Shipyard in May 1990 (October 20, 1988, Project 11660 - according to other data). The following were laid down works # 952 and 953, Project 1161, and the lead ship, Project 11660 (factory # 901). The development of working design documentation for Project 11662 has begun.

In 1991, an initiative study was presented, and later an abbreviated technical project of the multipurpose SKR pr.11663 - a variant of the SKR pr.11660 with a helicopter, URO, air defense, PLO and with BIUS. When choosing the TFR for the construction of the Navy, he preferred pr.12441 TsMKB "Almaz" (which was never built), and the development of the TFR projects pr.11660 and pr.11663 were closed in 1992 by the Resolution of the Council of Ministers of Russia. Work on Project 11662 has been continued so far.

In July 1993, the lead ship, project 1161, factory # 951, was launched and its completion began. In February 1995, a crew arrived in Zelenodolsk to master the TFR. During 1995, a foreign customer (presumably, India) abandoned the ships No. 952 and 953 and their construction was stopped. At the end of 1995, the construction of the ship No. 951 was discontinued with 93% readiness, the crew was disbanded, the ship was mothballed due to lack of funding and due to the uncertainty of the customer (Russian Navy) between different types TFR.


Finishing construction afloat SKR pr.11661 serial number 951, Zelenodolsk Shipyard, presumably 1995 (Zelenodolsk Design Bureau. Checked by sea. 60 years 1949-2009 Kazan, Helicopter, 2009).


Between 1995 and 1998 Zelenodolsk Design Bureau developed a family of export projects "Gepard", completed a technical project "Gepard-3.9" for a foreign customer. In 1998, Project 11662 was closed and work on the laid down ship of the project was stopped when the ship was 11% ready.

In 2001, the leadership of the Navy made a decision to complete the construction of the ship No.951 for Project 11661K (the first with this project number) for the Caspian Flotilla under the name "Tatarstan". The submarine armament was removed from the ship, the project was corrected. In early April 2002, a crew arrived in Zelenodolsk to master the ship. In July 2002 the ship was inclined - the deviation from the calculated displacement was 1 ton. On July 12, 2002 "Tatarstan" left the water area of ​​the Zelenodolsk Shipyard and went to Makhachkala for testing. In May 2003, the SKR passed seaworthy tests at sea waves of 5 points. The ship was accepted by the Russian Navy as the flagship of the Caspian Flotilla on August 31, 2003.

According to unconfirmed reports, the last ship of the project for the Russian Navy was the Dagestan TFR. The construction of other ships of the project 1161K for the Russian Navy is apparently not planned. The conclusion was made, incl. based on the fact that the production of an artillery installation for the Russian Navy has been discontinued. Although, this may mean equipping new ships of modernized projects with a 100 mm installation or.


Design- the case consists of 10 waterproof compartments, the case material is low-alloy steel. The superstructure is made of corrosion-resistant aluminum-magnesium alloy. The ship retains its buoyancy and combat capabilities when any two adjacent compartments are flooded. The ship is equipped with an air conditioning system. There are active stabilizers.

During the construction of corvettes pr.11661E for the Vietnamese Navy, the Cherepovets Matellurgical Plant supplied two types of steel ():
- structural sheet of grade 10ХСНД;
- high-strength ship steel D40S.

Propulsion system:

project description
Project 11661 two-shaft diesel-gas turbine unit (GTU) of the CODOG type, consisting of two gas turbine engines (GTE) M-88 with a capacity of 10,000 hp each (15,000 hp at the stage of draft design) and a 61D economic diesel engine with a capacity of 8,000 hp, working through complex gearboxes on two shafts and two fixed-pitch propellers (FPP).
Project 1161K and Project 1161K "Dagestan"
a two-shaft diesel-gas turbine unit (GTU) of the CODOG type, consisting of two gas turbine engines (GTE) with a capacity of 14,825 hp each. and a diesel engine of economic progress 61D with a capacity of 8000 hp, working through complex gearboxes on two shafts and two fixed-pitch propellers (FPP).
Project 11661E "Gepard-3.9" According to reports on the website of the Zelenodolsk plant from 2011, the ship uses "unlike a gas turbine, an economical diesel power plant" - probably
"Cheetah-5.1" two-shaft diesel-diesel unit of the CODAD type, consisting of 4 MTU diesel engines with a capacity of 4700 hp each or a combination of 2 x 3300 hp. + 2 x 6500 hp diesel engines operating through complex gearboxes on two shafts and two fixed pitch propellers (FPP).
"Cheetah-5.3" two-shaft diesel-diesel unit of the CODAD type, consisting of 4 MTU diesel engines with a capacity of 4700 hp each or a combination of 2 x 3300 hp. + 2 x 6500 hp diesel engines operating through complex gearboxes on two shafts and two fixed pitch propellers (FPP).


Scheme of the power plant of the SKR pr.11660 (Zelenodolsk design bureau. Checked by the sea. 60 years 1949-2009, Kazan, Helicopter, 2009).


Zonal block of the Main Power Engineering Directorate of the SKR pr.11660 (Zelenodolsk Design Bureau. Checked by the sea. 60 years 1949-2009 Kazan, Helicopter, 2009).


Mechanics- during the tests of the lead ship, project 11661K "Tatarstan", vibration of the disconnecting clutch at high speeds was detected. In the course of improvements, vibration is reduced. And by 2003 the defect was completely eliminated by the efforts of engineer B.G. Lapin.

Energy- diesel generator (s) with a total capacity of 1800 kW

TTX ships:

Project 11661 / Project 11661K (first)
Project 11661K / Project 1161K "Dagestan"
Project 11661E "Gepard-3.9" "Cheetah-5.1" "Cheetah-5.3"
Crew 121 people (including 15 officers) 120 people (including 12 officers) 103 people (16 spare places) 79 people 102 people
Length 102.14 m 102.14 m 102.2 m 102.2 m 102.2 m
Waterline length 93.5 m 93.5 m
Width 13.9 m 13.9 m 13.6 m (13.1 m according to other data)
13.1 m 13.1 m
Maximum draft
5.3 m - 5.3 m 5.3 m 5.3 m
Draft overall 4.5 m
Draft without GAS 3.6 m 3.6 m 3.6 m
Full displacement 1930 t 1930 t 2100 t 2000 t 2100 t
Displacement standard 1500 t 1500 t
Full stroke speed 28 knots 28 knots 28 knots 25 knots 25 knots
Cruising speed
21 knots 21 knots (under a diesel engine, increased as a result of revision from 18 knots)


Economic speed
10-14 knots 10 knots 10 knots 10 knots
Sailing range
5000 miles (10 knots)
3,800 miles (14 knots)
1,750 miles (22 knots)
950 miles (27 knots)
4,000 miles (10 knots), 5,000 project miles
3,500 miles (14 knots)
950 miles (27 knots)
OK. 4,500 miles (10 knots) OK. 4,500 miles (10 knots)
Autonomy 15 days 15 days 20 days 30 days 20 days
Armament:
Project 11661 Project 11661K (first)
Project 11661E "Cheetah-3.9"
Project 11661To "Dagestan"
RCC 8 (2 PU KT-184 - 2 x 4 TPK) x 3K24 "Uran" complex with 3M24 / 3M24UD "Uran" anti-ship missiles - SS-N-25 SWITCHBLADE 8 (2 launchers KT-184 - 2 x 4 TPK) x 3K24 "Uran" complex with 3M24 / 3M24UD "Uran" anti-ship missiles - SS-N-25 SWITCHBLADE
8 (2 PU KT-184 - 2 x 4 TPK) x 3K24E "Uran-E" complex with 3M24E "Uran-E" anti-ship missiles - SS-N-25 SWITCHBLADE Universal Ship Firing Complex (UKSK) - installation of vertical launch of type 3S14E (in the bow of the ship) for 8 missiles of the Kalibr-NK missile system with a range of more than 300 km
SAM SAM 4K33 "" - 1 x 2 launcher ZIF-122 with ammunition 20 missiles 9M33 SAM 4K33 "" - 1 x 2 launcher ZIF-122 with ammunition 20 missiles 9M33


MANPADS 2 x "Igla-M" 2 x "Igla-M" 2 x "Igla-M" 2 x "Igla-M"
Artillery - 1 x 76 mm gun mount, 500 rounds of ammunition - 1 x 76 mm gun mount, 314 rounds of ammunition In the original version -
- 1 x 76 mm artillery mount with the SUO 5P-10 "Puma"
Auxiliary weapons 2 х 7.62 mm PKT machine gun 2 x 14.5 mm KPVT machine gun on MTPU mounts, 2 x 7.62 mm PKT machine gun
2 х 14.5 mm KPVT machine guns on MTPU mounts 2 х 14.5 mm KPVT machine guns on MTPU mounts
ZRAK / AK 2 x, ammunition 2 x 2000 rounds 2 x, ammunition 2 x 2000 rounds
1 combat module 3R89 ZRAK "" with 2 x 4 PU SAM 9M340E


Shooting from the AK-176 artillery mount during the tests of the first ship of the project "Gepard-3.9" for the Vietnamese Navy No. 954, 2010 (http://www.zdship.ru).


Shooting from the installation of the combat module ZRAK "Palma" during the tests of the first ship of the project "Gepard-3.9" for the Vietnamese Navy No. 954, 2010 (http://www.zdship.ru).



Tests of the AK-630M artillery mount on the second ship of the Gepard-3.9 project for the Vietnamese Navy, serial number 955. The containers of the X-35 "Uran" anti-ship missile launcher are clearly visible. 2011 (http://www.zdship.ru).


Tests of the second ship of the project "Gepard-3.9" for the Vietnamese Navy, serial number 955. Landing of the Ka-27 helicopter. 2011 (http://www.zdship.ru).


Equipment:
Project 11661 NS.11661 K (first)
Project 11661E "Cheetah-3.9"
Project 11661To "Dagestan"
BIUS Sigma? / OTs-11661 Sigma? / OTs-11661 "Sigma-E" / OTs-11661 (?)
Sigma / OTs-11661 (?)
Radar for detecting air and surface targets MP-352 "Positive" / CROSS DOME MR-352ME1 "Positive-ME1" / CROSS DOME MP-352 "Positive-M1" / CROSS DOME
RCC target designation radar 34K1 "Monolith" / BASS STAND on the built ship. Probably in the early project was "Harpoon-Ball" / BAND STAND 34K1 "Monolith" / BASS STAND

During the exercise on 12/12/2011, an improved anti-ship missile guidance complex was tested

34K1 "Monolith" / BASS STAND 34K1 "Monolith" / BASS STAND

"Mineral-M" (according to other data)

Navigation radar "Kivach" "Kivach" / "Volga" / PALM FROND
MR-212 "Vaygach" MR-212 "Vaygach"
Artillery radar MP-123/176 "Pennant" - BASS TILT MP-123/176 "Vympel" - BASS TILT / "Laska" - in the initial version of the project.
MP-123/176 "Pennant" - BASS TILT
Radar of stern artillery installations MP-123 - BASS TILT MP-123 - BASS TILT
Radar air defense system 2P33 / POP GROUP 2P33 / POP GROUP MP3-301 "Base" / POP GROUP
Navigation inertial system
SJSC "Zarnitsa" MGK-335M, mid-frequency range, under-keel antenna post GAS and towed GAS
-
"Zarnitsa" MGK-335ME-03, mid-frequency range, under-keel antenna post GAS and towed GAS -
Towed GUS medium frequency range, towed hydroacoustic suppression device "Serpent" -
medium frequency range, towed hydroacoustic suppression device "Serpent"
-
Electronic countermeasures complex "Start" 2 direction finders BELL SHROUD, 2 jamming stations BELL SQUAT, complex ASOR-11661 "Start"
- 2 direction finders TK-25E / BELL SHROUD
- 2 BELL SQUAT jamming stations
- ASOR-11661 complex
electronic warfare complex TK-25
2 direction finders BELL SHROUD, 2 jamming stations BELL SQUAT, complex ASOR-11661
Laser detection station "Spectrum-F4" / "Spectrum-FN"
"Spectrum-F4" / "Spectrum-FN" "Spectrum-F4" / "Spectrum-FN"
Communication complex "Rusich-4K" (data transmission equipment)
General operational control system "Angle"


Weapon systems and equipment on the frigate pr.11661E "Gepard-3.9" serial number 954 - the first for the Vietnamese Navy, photo 2010 (http://www.zdship.ru).


The main antenna posts of the SKR radar pr.11661K "Dagestan", Novorossiysk, October 2011 (http://www.militaryphotos.net).


Modifications:
Project 11660"Cheetah"- project of coastal TFR / anti-submarine ship, chief designer - M.M. Nesterenko (since 1986 - V.N. Kashkin).
- 1983 - design began as a TFR, the readiness of the lead ship for weapons systems was assessed by 1992.

- 1984 December - the Resolution of the USSR Council of Ministers was adopted on the development of export TFR pr.11661, TFR for the USSR Navy pr.11660 and PSKR pr.11662.
- 1985 start - draft project 11661 with a CODOG-type propulsion system (diesel + two gas turbine engines) completed.
- 1986 beginning - completed the technical design of the SKR pr.11661. The USSR SME set the task of unifying the ships of Project 1160 and Project 1161 by 85% and work began on re-assembling the projects.
- 1986 - the chief designer of the project, M.M. Nesterenko, for health reasons, asks to be relieved of his post and V.N.Kashkin is appointed instead.
- 1986 beginning of September - the beginning of the defense of projects 11660, 11661 and 11662. After modifications for the Uran missile complex, the Zarya complex and other equipment, the concept of the "Basic platform for a family of ships" was finally formulated.
- 1987 beginning - approved the technical project of pr.11661. The task was set in the development of the technical project of Project 11660 to ensure unification with Project 1161 by 80%. The processing of the technical project of Project 11660 has begun.
- 1990 - laid down the lead ship of Project 11660 (serial number 901) - the laying took place after the laying of the first three ships of Project 1161.
- 1992 - the development of the SKR project 1160 was closed by the Resolution of the Council of Ministers of Russia. Construction stopped. According to some reports, the groundwork has been disassembled on the slipway.

Project 11660E / pr. 11661"Cheetah" / pr.11661K (first)- initially export option SKR pr.11660, later - missile ship / SKR, chief designer - M.M. Nesterenko (since 1986 - V.N. Kashkin).
- 1983 April - the beginning of the study of the project during the development of pr.11660 as a TFR. The readiness of the lead ship in terms of weapons systems was estimated by 1990.
- 1984 - 1 Central Research Institute of the Ministry of Defense of the USSR put forward a requirement to equip the TFR with the Uranium anti-ship missile complex, the development of which was planned to begin in 1987.
- 1984 December - the Resolution of the Council of Ministers of the USSR was adopted on the development of the export TFR pr.11661 based on pr.11660.
- 1985 beginning - completed draft project 1161 with a CODOG-type propulsion system (diesel + two gas turbine engines).
- 1986 beginning - completed the technical design of the SKR pr.11661. The USSR SME set the task of unifying the ships of Project 11660 and Project 1161 by 85%, and work began on re-assembling the projects under a single constructive platform.
- 1986 beginning of September - the beginning of the defense of projects 11660, 11661 and 11662. After modifications for the complex anti-ship missiles "Uran", SJSC "Zarya" and other equipment, the concept of "Basic platform" was finally formulated.
- 1987 beginning - approved the technical project of pr.11661.
- 1987 - with the use of the concept "Basic platform" Zelenodolsk Design Bureau began to issue working design documentation for pr.11661.
- End of 1987 - the creation of a reserve for the head ICR pr.11661 at Zelenodolsk Shipyard began.
- 1988 - the final technical project of project 1161 was approved, the development of working design documentation began.
- 1990 May - the head SKR pr.11661 (factory # 951) was laid down at the Zelenodolsk Shipyard. Serial works # 952 and 953 of Project 1161 and the lead ship of Project 11660 (factory # 901) were laid next.
- 1993 July - the lead ship of Project 11661, factory # 951, was launched, its completion began.
- 1995 February - a crew arrived in Zelenodolsk to master the TFR pr.11661.
- 1995 - a foreign customer (presumably, India) abandoned the ships No. 952 and 953, pr.11661, and their construction was stopped.
- 1995 end - construction of the ship No.951 was stopped with 93% readiness, the crew was disbanded, the ship was mothballed due to lack of funding and due to the uncertainty of the customer (Russian Navy) between different types of TFR.
- 2001 - the leadership of the Navy made a decision to complete the construction of the ship No. 951 on Project 11661K (the first with this project number) for the Caspian flotilla under the name "Tatarstan". The submarine armament was removed from the ship, the project was corrected.
- 2002 early April - a crew arrived in Zelenodolsk to master the ship.
- 2002 July - the ship was inclined - the deviation from the calculated displacement was 1 ton.
- 2002 July 12 - "Tatarstan" left the water area of ​​the Zelenodolsk Shipyard and went to Makhachkala for testing. - 2003 May - SKR passed seaworthy tests at sea level 5 points.
- 2003 August 31 - TFR / missile ship "Tatarstan" adopted by the Russian Navy as the flagship of the Caspian Flotilla.


Anti-submarine TFR pr.11661 factory # 951 before restructuring on pr.11661K at the outfitting wall of Zelenodolsk Shipyard, photo 1995-2000. (http://forums.airbase.ru).


SKR pr.11661K "Tatarstan" factory # 951 ("Sea policy of Russia", 2005).


SKR pr.11661 and missile ship pr.11661K "Tatarstan" (http://forums.airbase.ru).


Project 11662 / 11662P- Border TFR, project, chief designer - M.M. Nesterenko (since 1986 - V.N. Kashkin).
- 1984 December - the Resolution of the USSR Council of Ministers was adopted on the development of the export TFR pr.11661, the TFR for the USSR Navy pr.11660 and the frontier TFR pr.11662.
- 1985 - developed an addition to the draft pr.11660 according to the PSKR pr.11662.
- 1986 beginning of September - defense of projects 11660, 11661 and 11662 began.
- 1987 the beginning - using the concept "Basic platform" Zelenodolsk Design Bureau began the development of technical projects pr.11660 and pr.11662.
- 1988 - Project 1162 is being adjusted taking into account the wishes of the USSR Border Troops.
- 1990 - the development of working design documentation for pr.11662 began.
- 1992 - after the closure of work on Project 11660 and Project 1163, work on Project 11662 continued.
- 1998 - Project 11662 was closed and work on the laid down ship of the project (No.971) was stopped when the ship was 11% ready.


Project 11663- SKR / corvette, project, chief designer - V.N. Kashkin.
- 1991 - an initiative study was presented, and later an abbreviated technical project of the multipurpose SKR pr.11663 - a variant of the SKR pr.11660 with a helicopter, URO, air defense, PLO and with BIUS. When choosing the TFR for the construction of the Navy, he preferred project 1244.1 of the Almaz TsMKB (which was never built).
- 1992 - development of projects of the SKR pr.11660 and pr.11663 closed in 1992 by the Resolution of the Council of Ministers of Russia.


Model SKR pr.11663 (Zelenodolsk Design Bureau. Checked by sea. 60 years 1949-2009, Kazan, Helicopter, 2009).

"Cheetah-1"- a variant of the export TFR based on pr.11660 - instead of a towed GAS - a helipad, without a hangar for a helicopter, the Osa-M air defense missile system. Developed in the late 1990s.

"Cheetah-2"- a variant of the export TFR based on the project 11660 - instead of a towed GAS - a helipad with a hangar for storing a helicopter, there is no Osa-M air defense system. Developed in the late 1990s.

"Cheetah-3"- a variant of the export TFR on the basis of pr.11660 - instead of the air defense missile system and the ZAK, the installation of the aft and bow combat modules of the ZRAK "Kortik" was proposed. The length of the hull is increased by 13.8 m. The displacement is up to 2100 tons. ZRAK "Kortik" (according to the original project), a helipad above the compartment of the towed GAS. Developed in the late 1990s.

"Cheetah-4"- a variant of the export TFR based on the project 11660 - a platform ship for the installation of weapons and equipment of the customer or a search and rescue vessel. Developed in the late 1990s.

"Cheetah-5"- a variant of the export frontier TFR based on pr.11660 - a helipad without a hangar, the composition of weapons systems has been changed. range increased to 6,000 miles (at 10 knots). Maximum speed reduced to 23 knots. GTEs in the propulsion system were replaced by diesels with a total power of 28,000 hp. Developed in the late 1990s.

Project 11661E "Cheetah-3.9"- TFR / coastal corvette. Two ships were built for the Vietnamese Navy. The contract was signed in 2006. The head ship # 954 was laid down on July 10, 2007, launched on December 12, 2009, sent to the customer by the carrier from Baltiysk, probably on December 10, 2010. The lead ship successfully passed mooring and sea trials, performed test firing of the Uran anti-ship missile system in the Baltic. On March 5, 2011 the flag of the Vietnamese Navy was raised on the ship and the ship was named "Dinh Tien Hoang". It is unlikely, but it is possible that during the construction of the ships the backlog of the ships of Project 11660 and Project 11662 was used, the construction of which was discontinued in 1992-1998.


The original view of the TFR pr.11661 "Gepard-3.9" (http://forums.airbase.ru).


The final view of the TFR / frigate pr.11661 "Gepard-3.9", 2010 (http://www.zdship.ru).


SKR pr.11661E "Gepard-3.9" for the Vietnamese Navy at the outfitting wall of the Zelenodolsk Shipyard, on the left - No 955, on the right - No 954. March 16, 2010 (photo from the Denis KA archive, http://forums.airbase.ru, http://www.zdship.ru).


The second head No. 955 of the TFR pr.11661E "Gepard-3.9" for the Vietnamese Navy at the outfitting wall of the Zelenodolsk Shipyard, 20.07.2010 (http://maps.google.com).


TFR / corvette No.954 pr.11661E "Gepard-3.9" (the first for the Vietnamese Navy) in Kronstadt before the installation of some of the equipment, summer 2010 (http://forums.airbase.ru).


SKR / corvette No.954 pr.11661E "Gepard-3.9" (the first for the Vietnamese Navy) at the wall of the Kronstadt Marine Plant during testing in the Baltic. 08/14/2010 (photo Mike1979, http://en.wikipedia.org).


SKR / corvette No.954 pr.11661E "Gepard-3.9" (the first for the Vietnamese Navy) during testing in the Baltic. August-autumn 2010 (http://www.militaryphotos.net).


The first ship of the project "Gepard-3.9" for the Vietnamese Navy - serial number 954 - at the final stage of testing, 2010 (http://www.zdship.ru).


Project 11661TO- TFR / corvette for the Caspian Sea / missile ship, modification of Project 1161 / 11661K (first) with modified armament. The lead ship, No. 952, was laid down in 1990 as the ship of Project 1161, was completed according to the modified Project 1161K as "Dagestan" since 2002. It should have been launched according to plan in 2010, later - in March 2011, actually launched on April 4, 2011. Commissioning is planned for 2011 (plans for 2010). The second serial ship, probably No. 953 Burevestnik, is in the shops of Zelenodolsk Shipyard. On September 13, 2011, the Dagestan TFR left Zelenodolsk for Novorossiysk to undergo tests, which should begin on October 1, 2011. In 2012, the ship is planned to be accepted into the Navy.



Status: Russia
- 1995 - work on the construction of orders Nos. 952 and 953 was stopped due to the refusal of the foreign customer from these ships.

2002 August 09 - during the visit of the Minister of Defense of Russia S.B. Ivanov to the Zelenodolsk Shipyard, a decision was made to build the second ship, project 1161K. Probably, work on completion of project 1161K of the Dagestan missile ship began in 2005 or earlier.

2003 September - the rocket ship "Tatarstan" successfully carried out an operation to rescue the ship "Russia" in a storm in the Caspian Sea.


- 2005 March 24 - general manager Zelenodolsk Shipyard named after AM Gorky (Tatarstan) S. Ilyin told the media that in 2007 it is planned to transfer the frigate "Dagestan" to the Caspian Flotilla. He also said that the Navy this year, compared with the previous one, has multiplied its funding for the construction of the ship. Today the state defense order in total volume marketable products Zelenodolsk shipyard is 15-23%. It is assumed that with the planned increase in production volumes from 1.6 billion rubles. in 2005 up to 3 billion rubles. in 2007 the share of the state defense order will remain unchanged.


SKR pr.11661K "Tatarstan" factory # 951 at the parade on Navy Day in Astrakhan, July 29, 2007 (photo by Alexei_s, http://photofile.ru/users/alexei_s).


- 2009 December 12 - the first hull No. 954 of the SKR / frigate of the Gepard-3.9 project for the Vietnamese Navy was launched.


Launching of the SKR / frigate of the project "Gepard-3.9" No. 954 for the Vietnamese Navy, Zelenodolsk, 12.12.2009 (http://www.zdship.ru).


- 2010 July - SKR pr.11661E factory # 954 was planned to be transferred by inland waterways to the Baltic for revisions and testing.

2010 August - SKR pr.11661E, serial number 954, as of August 14, is at least in the Baltic (Kronstadt) to undergo the final stage of sea trials. According to the information on the website of the Zelenodolsk plant, the second ship No. 955 was also sent to Baltiysk.

2010 November - SKR pr.11661E serial number 954 arrived in Baltiysk to complete tests and load on a carrier ship for shipment to the customer - the Vietnamese Navy. Arrival in Baltiysk took place no later than November 24, 2010. Test launches of the Uran anti-ship missile system were carried out in the Baltic.

2010 09 December - SKR pr.11661E factory # 954 entered the shipyard "Yantar" (Baltiysk) to be loaded onto a carrier ship. The staging operation was to take 1 day. The probable date of departure to Vietnam is 12/10/2010.

2011 09 February - General Director of Zelenodolsk Shipyard Renat Mistakhov said that the launch of the Dagestan TFR will take place in March 2011, and in May 2011 the ship will leave for the place of service in the Caspian Sea.

2011 April 01 - Investigative Committee of the Russian Federation "Dagestan" pr.11661K, factory # 952, was removed from the closed boathouse and launched at Zelenodolsk Shipyard.


Withdrawal of the ICR "Dagestan" pr.11661K from the closed boathouse for launching into the docking chamber "Volga", Zelenodolsk, 01.04.2011 (http://www.zdship.ru).


- 2011 April 21-22 - sea and state tests of the ship No. 955 of the project "Gepard-3.9" for the Vietnamese Navy have been successfully completed.

2011 May 17 - The media report that the Tatarstan ICR, pr.11661K, is undergoing scheduled repairs at the Volga-Caspian Shipyard and in June 2011, after sea trials, will return to the fleet.


http://www.zdship.ru).


2011 September 13 - SKR "Dagestan" pr.11661K began the transition from Zelenodolsk Shipyard to Novorossiysk for testing. The crossing is carried out by inland waterways.


Sections of the body of order No. 953 from the assembly shop were moved outside for disassembly. The data has not been confirmed. September 26, 2011 (http://forums.airbase.ru).


TFR pr.11661K "Dagestan" arrived for testing in Novorossiysk, October 01, 2011 (photo by sdn82, http://forums.airbase.ru).


- 2011 November 09 - the media announced that the TFR "Dagestan" pr.11661K will be accepted into the Caspian flotilla by the end of 2011.

2011 early November - according to media reports, confirmed by eyewitnesses and video recordings, the Dagestan TFR, while in the port of Novorossiysk in a storm, seriously damaged the starboard side. The reason for what happened is that the commissioning team from the Caspian Sea did not manage to take the ship away from the quay wall during a stormy gust. The damage is planned to be repaired on site.


Fragment of the damage area of ​​the Dagestan ICR, pr.11661K, November 2011 (video fragment from social network vkontakte.ru)

- 2011 December 12 - during the started exercises of the ships of the Caspian Flotilla at the TFR "Tatarstan" it is planned to test an improved anti-ship missile guidance complex.

2011 December 27 - the media announced that the Dagestan ICR, pr.11661K, has completed the first stage of sea trials and is starting tests of the Kalibr-NK missile system.

2012 January 25 - the media reported that the cost of repairing the damage received by the Dagestan Investigative Committee during a storm in November 2011 is 60 million rubles. Repairs are carried out by Zelenodolsk Shipyard at the berth wall in Novorossiysk.


- 2012 07 February - the media reported that the TFR "Dagestan" pr.11661K will be accepted into the Caspian fleet in the first half of 2012.

2012 May 25 - the first stage of the state testing of the Dagestan TFR, pr.11661K, was completed on the Black Sea. During the first stage of testing, the Kalibr-NK missile system was successfully fired for the first time. The ship is preparing for the passage to the Caspian by inland waterways.


SKR pr.11661K "Dagestan" serial number 952 at the parade on the Day of the Navy in Astrakhan, July 29, 2012 (photo - Evgeny Lukovtsev, 11356. There is a version that the customer was "persuaded" to refuse the order of the TFR pr.11661.

Vietnam:
- 2006 December - a contract was signed for the construction of two ships pr.11661E for the Vietnamese Navy, with the possible production of subsequent ships of the project at enterprises in Vietnam.

2007 - construction of 2 SRK / frigates pr.11660 (option) for the Vietnamese Navy began. The handover to Vietnam is planned for 2010.

2010 - ships are being completed and tested.

2010 December 10 - the estimated date of dispatch of the TFR / frigate No. 954 to Vietnam on the carrier ship. The shipment was made from the Yantar shipyard (Baltiysk).


The second ship of the project "Gepard-3.9" for the Vietnamese Navy - serial number 955 - at the final stage of testing, 2011 (http://www.zdship.ru).


- 2011 March 5 - the flag of the Vietnamese Navy was raised in the Kam-Ran naval base on the TFR / frigate No. 954 and the ship was named "Dinh Tien Hoang".


The ceremony of raising the flag on the frigate "Dinh Tien Hoang" of the "Gepard-3.9" project, Kam Ranh naval base, Vietnam, 05.03.2011 (http://www.zdship.ru).


- 2011 May 25 - after the completion of the tests of the second TFR / frigate of the project "Gepard-3.9" departed for Vietnam on the carrier ship Eida Transporter.

2011 August 22 - the second frigate of the "Gepard-3.9" project was transferred to the Vietnamese Navy. The frigate is named Lee Thay To. Home port - Kam-Ran.

2011 December 7 - the media reported on the conclusion of a contract with Rosoboronexport for the supply of an additional 2 Gepard-3.9 frigates in an anti-submarine configuration.


Corvette "Dinh Tien Hoang" (HQ-011) pr.11661E docked in Da Nang, Vietnam, 2012 (photo - Evanna Lynch, http://www.militaryphotos.net).


Corvette "Dinh Tien Hoang" (HQ-011) pr.11661E in Da Nang, Vietnam, 2012 (photo - Evanna Lynch, http://www.militaryphotos.net).


- 2013 March 27 - The media reported that in 2013 it is planned to conclude a new contract for the construction of two corvettes pr.11661E "Gepard-3.9" for the Vietnamese Navy. The laying of the first ship will take place in June 2013. Delivery to the customer is planned for 2016 and 2017. (). Steel grades 10ХСНД and D40S for the construction of ships will be supplied by the Cherepovets Matellurgical Plant ().


Patrol ship HQ-011 Đinh Tiên Hoàng pr.11661E ("Cheetah-3.9") of the Vietnamese Navy and the Chinese frigate Huangshan of project 054A. Gulf of Tonkin, 20.06.2013 (photo - Mr. Do, http://www.thanhnien.com.vn/ via http://bmpd.livejournal.com/).

- 2013 September 24 - at the Zelenodolsk Shipyard, the laying ceremony of two TFR pr.11661E "Gepard-3.9" with anti-submarine weapons is planned. The construction will be carried out on the basis of an intergovernmental contract dated 17.10.2012 and under a contract between JSC Rosoboronexport and JSC Zelenodolsk Plant named after A.M. Gorky dated 15.02.2013.

2013 December 18 - at Zelenodolsk Shipyard signed the Act of Completion of Stage 1 (ordering, manufacturing of hull and superstructure sections) for the construction of the first of a pair of frigates "Gepard-3.9" with anti-submarine weapons ().


Register of TFR / corvettes pr.11660 / 11661 etc.:


project plant.№ plant laid launched entered service note
"Tatarstan" / SKR-200
Project 11661K 951 May 1990
July 1993

07/02/2001 (beginning of perestroika)

31.08.2003
Caspian flotilla
the ship was laid down on Project 11661, was almost completed at the end of 1995, construction was stopped due to lack of funding, it was being completed on Project 1161K, the name before "Tatarstan" is SKR-200; from 03.10.1996 - "Tatarstan"
"Dagestan" / SKR-201 / "Albatross"
Project 11661K 952 Zelenodolsk
Shipyard named after A.M. Gorky
(1990?)
plan 2010 (2009)

launched 04.04.2011

plan - 2007 (announced in 2005)

plan for 2011?
Caspian flotilla

2012 (plans for September 2011)

December 2011 (plans 09.11.2011)

plans - the first half of 2012 (07.02.2012)

28.11.2012

was laid down on Project 11661 as "Albatross", was built probably for India, construction was stopped in 1995 due to the customer's refusal to purchase, later renamed SKR-201; since 2010 at least - "Dagestan"
"Petrel" NS. 11661TO? 953 Shipyard named after Zelenodolsk A.M. Gorky (1990?)
there is no data no data, Caspian flotilla was laid on the project 1161 "Burevestnik", was built probably for India, the construction was stopped in 1995 due to the refusal of the customer to purchase, in the construction

On September 28, 2011, the unfinished sections of the hull were moved from the assembly shop to the outside for subsequent disassembly. The data has not been confirmed.

Hawk? Project 11660 901 Zelenodolsk
Shipyard named after A.M. Gorky
(1990?) - - dismantled on the slipway in the 1990s, the project is closed
there is no data Project 11662 / 11662P
971 Zelenodolsk
Shipyard named after A.M. Gorky
1991-1995
- - construction was stopped in 1998 with 11% readiness, the project is closed
"Dinh Tien Hoang" (HQ-011) Project 1161E
"Cheetah-3.9"
954 Shipyard named after Zelenodolsk A.M. Gorky 10.07.2007 12.12.2009 plan - November 2010

probably, on 10.12.2010 departed for Vietnam on a carrier ship

05.03.2011

No. 1 for the Vietnamese Navy, during the tests, board No. 415. The flag of the Vietnamese Navy was raised on 03/05/2011.
"Ly Thay To" (HQ-012) Project 1161E
"Cheetah-3.9"
955 Zelenodolsk
Shipyard named after A.M. Gorky
27.11.2007 16.03.2010 plan - 2010 (not implemented)

05/25/2011 departed for Vietnam on the Eida Transporter

08/22/2011

No. 2 for the Vietnamese Navy, during the tests, board No. 416. The flag of the Vietnamese Navy was raised on 08/22/2011.
No. 3 for the Vietnamese Navy Project 1161E
"Cheetah-3.9"
956 Zelenodolsk
Shipyard named after A.M. Gorky
plan - June 2013 (March 2013)

plan - September 2013 (05.07.2013)

- plan - 2016 (March 2013, confirmed on 07/05/2013)

plan - 09.24.2013 (09.20.2013)

- plan - 2017 (March 2013, confirmed on 07/05/2013 and 02/26/2014) No. 4 for the Vietnamese Navy
It is being built under an intergovernmental contract dated 17.10.2012 and a contract between JSC Rosoboronexport and JSC Zelenodolsk Plant named after A.M. Gorky dated 15.02.2013.
Italic the presumptive data are highlighted.

Board numbers:

FlotProm is a naval military-industrial complex. Website http://flotprom.ru/, 2011
Balancer.Ru, forums. Site
Year "Tatarstan" office # 954 office # 954 "Dagestan"
2003 r. 691


2010 r.

Project 11661 (code "Gepard", according to NATO codification - Gepard) is a type of patrol ships of the Russian and Vietnamese fleets. Ships of the series have been built at the Zelenodolsk plant named after A.M. Gorky since 1990.

In the early 1980s, it became necessary to develop a new coastal patrol ship. It was supposed to replace the ships of Project 1124. This was due to the change in the purpose of the patrol ships of Project 11540, which in the final version were supposed to replace the larger patrol ships of Project 1135. The Zelenodolsk Design Bureau headed by chief designer Yu. A. Nikolsky, and then V.N.Kashkin.

Due to the requirements of the Navy for the placement of a powerful sonar station, the ship's displacement increased to 2000 tons, which became close to the ships of the competing project 12441. Those were distinguished by more powerful anti-ship missiles and the presence of a helipad.

At the end of 1990, the lead ship of Project 11660 was laid down, which was named Burevestnik, but after a while its construction was stopped. In 1995, its construction was discontinued and the ship was mothballed. The ship was later dismantled.

The second ship was laid down in 1993 under the export project 11661 for the Indian Navy, but in 1995, when it was almost ready, funding stopped. Later, it was completed according to the project 11661K, adjusted for the Russian Navy, and launched under the name "Tatarstan"; it entered service on August 31, 2003 and became the flagship of the Caspian Flotilla.

The third TFR was also founded according to the 11661K project in 1991 and was named "Dagestan". Its delivery to the fleet was originally planned for the first half of 2012, but was postponed due to damage received in January 2012 during mooring trials on the Black Sea near Novorossiysk. In July 2012, after restoration and repair work, "Dagestan" entered the Caspian Sea as part of the second stage of state tests for the implementation of missile firing at a coastal target from the "Caliber-NK" missile system. Shooting at a distance of 100 nautical miles was successful and on November 28, 2012, "Dagestan" became part of the Russian Navy.

The patrol ships of the project 11661 "Cheetah" have a traditional flat-deck architecture with 10 watertight compartments. The ship's superstructure is made of aluminum-magnesium alloys to ensure low visibility (the so-called stealth technology).

The patrol ships of the project 11661 "Gepard" have powerful missile, anti-aircraft missile and artillery weapons. The main ships of Project 11661E and the RK Tatarstan are the Uran (Uran-E) anti-ship missile system with Kh-35 (E) cruise missiles, having a firing range of up to 130 km (up to 260 km for Uran-U with missiles Kh-35U). Project 11661K ship, Dagestan, is the first Russian Navy ship armed with the Kalibr-NK universal missile system, which can use several types of high-precision cruise missiles capable of striking surface, underwater and coastal targets at a distance of up to 300 km.

Artillery armament includes a 76.2 mm bow artillery mount AK-176M (ammunition - 152 rounds) and two 30 mm automated artillery mounts AK-630M with an ammunition load of 2000 + 1000 rounds each, which ensures the fight against sea, ground and air targets. The rocket ship "Dagestan" also has two 14.5 mm naval pedestal machine gun mounts.

For air defense on ships of projects 11660 and 11661, as well as on the RK "Tatarstan" the anti-aircraft missile system "Osa-MA-2" with ammunition of 20 missiles is used. On the ship "Dagestan" instead of the OSA-MA-2 air defense system and two AK-630s, the ZRAK "Broadsword" is installed), and on the ships of the project 11661E, its export modification - "Palma" is installed on the forecastle, while both AK-630s are installed in aft superstructure side by side.

As anti-submarine weapons on the ships of pr. 11660 and 11661, two twin-tube 533 mm torpedo tubes were provided. On the ships of Project 11661E, one RBU-6000 rocket launcher is used as anti-submarine and anti-torpedo weapons. It is possible to equip ships with other weapon options, including the Ka-27 ship-based anti-submarine helicopter.

At different times, the ships were equipped with various radar and radio-electronic means. Thus, the ships were equipped with the 34K1 "Monolith" radar system, the MR-352 "Pozitiv" general detection radar, the MR-212 "Vaigach" navigation radar, the MR-123 "Vympel" artillery fire control system and the "Zarnitsa" GAS. The anti-sabotage OGAS MG-757 Anapa-M is installed on the Tatarstan ship. To control the firing of RBU on ships of pr. 11660 and 11661, PUSB "Tempest" was used, on ships of pr. 11661E, PUSB "Purga-ME" was used. The electronic warfare complex consisted of two KL-101 launchers of the REP PK-16 system or of four KT-216 launchers of the PK-10 "Brave" complex.

On the RK "Dagestan", the "Monolit" radar was replaced by "Mineral-M", and the general detection radar was replaced by "Positive-M1". Also installed hydroacoustic complex (GAK) type MGK-335, electronic warfare system TK-25 and BIUS "Sigma". Ships of the project 11661E are equipped with equipment similar to those installed on the "Dagestan" in the export version with some differences in its composition.

The main power plant is two-shaft, type CODOG. Medium-speed diesel engine type 61D with a capacity of 8000 liters. with. through a complex gearbox provides all cruising modes, and two gas turbines with a total capacity of 29,000 liters. with. (one for each shaft) provide the full speed of the ship up to 28 knots. The power plant includes three diesel generators of 600 kW each.